No Peter,
In the previous versions when you dropped the View menu there was a selection to \"View Cost/Price\" that would display the Dynamic pricing at the bottom of the screen if you selected yes to Dynamic Cost Display in Preferences.
Kerry
Thanks Dan,
I see they have a drop down menu on the Create Cost Sheet Icon to get the numbers.
I will miss the Dynamic Cost Display. I used it to get immediate feedback on how different things affected the cost.
Kerry
It has been a while since I used the program and I am getting things set up again. Am I reading this correctly, that we will not be able to see the cost at the bottom of the screen anymore??
And, I agree with Kerry; I will miss this display as well. Unless the programers will wiggle their noses once more to incorporate the best of both worlds.
Jeremy,
It is still re-calculating every time you make a change, you just can't see it now. The old way did allow you to turn it on and off in Preferences.
Kerry
DanEpps wrote:...I seem to remember Larry discussing removing the dynamic cost feature because it was a huge memory/performance hit.
Kerry Fullington wrote:...It is still re-calculating every time you make a change, you just can't see it now. The old way did allow you to turn it on and off in Preferences...
These two don't jive. If the dynamic price/cost was removed due to its effect on performance, but the program still IS doing it in the background, then it is a simple matter of displaying. Is it the "displaying" part that will give performance such a bad hit?
I would have thought that updating the cost/price data base in the background would cause the biggest hit on performance. BUT it could be that it is the same data base that keeps track of all the pieces and components of the cabinets; in this case, yes, everything is being changed dynamically every time one makes a change. But I also am NOT a systems guy - I am only a user.
What would be my preference? Make it an option to have it calculated or not (IF it does not cause a deterioration on performance, AND if possible to do so). And make it another option to display or not.
I'm not so sure costs are recalculated with every change. If you pick one of the options on the cost sheet dropdown menu it calculates costs before displaying the report.
One thing is strange though. When I go into Settings/Preferences and click the Define Costs button, it takes a full 10 seconds for the dialog to be displayed. Other buttons (Define Stock Materials, Define Standard Dimensions) are instantaneous.
The Dynamic Cost display feature is being phased out. We unfortunately forgot to remove the radio buttons in Dynamic Markups dialog. Sorry for the confusion.