Installing the sink
Moderators: Jason Susnjara, Larry Epplin, Clint Buechlein, Scott G Vaal, Jason Susnjara, Larry Epplin, Clint Buechlein, Scott G Vaal
-
- New Member
- Posts: 24
- Joined: Wed, Oct 22 2008, 11:06AM
Installing the sink
Hello everyone. I am attempting to design and bid my first kitchen with ecaqbinets and not doing to bad. Ran into a major snag trying to place the sink. I did a cut through in the counter top but can't seem to get the sink off the floor in the middle of the kitchen. The other snag is I can't seem to get the door and drawer fronts on the customer view.
Thanks

-
- Guru Member
- Posts: 477
- Joined: Tue, May 17 2005, 1:55PM
Re: Installing the sink
Bob -- Highlite the sink and use the SHIFT key and up ARROW at the same time. As for the D & Ds make sure that they aren't checked to HIDE them.
-
- Wizard Member
- Posts: 1896
- Joined: Wed, May 18 2005, 7:54PM
- Company Name: Milltech Millworks Ltd.
- Country: CANADA
- Location: Edmonton, Alberta
- Contact:
Re: Installing the sink
Hey Bob, go to Show/Hide and see if you have Doors and Drawer Fronts checked.
Re: Installing the sink
Associate the sink to the wall, then when you go to the elevation view you can move it up to the desired height either by entering positional information on the left. dragging it to location or using move increment methods.
The key to selecting the sink is that it must be associated to the wall.
The key to selecting the sink is that it must be associated to the wall.